North Shore Wastewater Treatment Plant

The Metro Vancouver plant whose cost estimate rose from roughly $700M in 2013 to $3.86B by 2024, and the share North Shore taxpayers carry.

15of 59 candidates have mentioned it
26times, in what I checked
Listed in randomised order within each race.

City of North Vancouver — Council

6 mentioned it · you elect 6

Smart Budget Optimization. We must prioritize needs over wants. I will push for a comprehensive financial review to focus funding on critical infrastructure, public safety, and core maintenance—ensuring your tax dollars are invested where they matter most, not on ideological pet projects.

Protecting Taxpayers from Wastewater Cost Overruns. North Shore taxpayers cannot absorb the majority of the costs for regional project failures. 8% of the region's population should not be liable for 37% of the cost.

North Shore Wastewater Treatment PlantTheir campaign sitesource · retrieved September 30, 2026

North Shore local government have been part of the problem....

…whether they don’t understand or don’t care, is not the issue

Building and maintaining sewage treatment plants is absolutely the responsibility of local governments whether they do it themselves, or delegate it to some other entity, it is a core responsibility of local government to ‘take care of …

The Harry Jerome Recreation Centre (HJRC) project is a great example of the problem of “bounded rationality”.

North Shore Wastewater Treatment PlantHarry Jerome Community Recreation CentreTheir campaign sitesource · retrieved September 30, 2026
Angela GirardElectedIncumbent

Press senior governments for an independent, public-facing review of the North Shore Wastewater Treatment Plant respecting its delivery, decisions and financial management of this capital project where costs have escalated from $700 million to $3.86 billion and the burden falls disproportionately on North Shore ratepayers

North Shore Wastewater Treatment PlantTheir campaign sitesource · retrieved October 14, 2026
Shervin ShahriariElectedIncumbent

I raised concerns about wastewater treatment plant costs and strongly supported calls for an independent public inquiry.

North Shore Wastewater Treatment PlantFiled statementsource · retrieved October 8, 2026

I raised concerns about wastewater treatment plant costs and strongly supported calls for an independent public inquiry.

My first term demonstrated the value of independent thinking.

North Shore Wastewater Treatment PlantFiled statementsource · retrieved October 8, 2026

I chaired the North Vancouver Museum & Archives Commission and City Library Board, and authored North Vancouver’s Lonsdale Neighbourhood, a local history book.

I supported North Shore Neighbourhood House redevelopment, including housing for families and workers. I championed pedestrian safety, accessibility, mature tree retention and heritage preservation. I raised concerns about wastewater treatment plant costs and strongly supported calls for an independent public inquiry.

North Shore Wastewater Treatment PlantFiled statementsource · retrieved October 8, 2026

Our city should responsibly and transparently manage the funds that residents and businesses provide. If we can effectively promote civic literacy more people will engage with city hall proactively and positively. Council must manage difficult financial decisions with our long-term interest in mind. This means incorporating the new community engagement framework into the next council’s strategic plan, following through on the call for a public inquiry into the wastewater treatment plant, and monitoring debt servicing and the health of our reserves.

North Shore Wastewater Treatment PlantTheir campaign sitesource · retrieved September 30, 2026

Council must manage difficult financial decisions with our long-term interest in mind. This means incorporating the new community engagement framework into the next council’s strategic plan, following through on the call for a public inquiry into the wastewater treatment plant, and monitoring debt servicing and the health of our reserves.

North Shore Wastewater Treatment PlantTheir campaign sitesource · retrieved September 30, 2026
Don BellElectedIncumbent

Finally, I fully support a truly independent public inquiry about Waste Water Treatment Plant costs, reducing future financial impact on our taxpayers and review of Metro Vancouver Regional District structure.

North Shore Wastewater Treatment PlantFiled statementsource · retrieved October 8, 2026

District of North Vancouver — Mayor

3 mentioned it · you elect 1

I am running for Mayor of the District of North Vancouver as an independent—with no slate and no party—because residents deserve a government that listens, explains how public money is spent, and takes responsibility when projects go off track. The North Shore Wastewater Treatment Plant is one example. Metro Vancouver’s estimate rose from about $700 million in 2013 to $3.86 billion in 2024. The plant is necessary, but residents deserve public reporting, independent oversight, and a fair allocation of costs. I will advocate for all three wherever the District has a seat at the table.

North Shore Wastewater Treatment PlantFiled statementsource · retrieved October 8, 2026

Making sure the North Shore isn't left carrying costs and consequences it didn't create.

We're being stuck with the heaviest burden of paying for the wastewater treatment plant's cost overruns, despite no direct accountability to North Shore voters at Metro Vancouver.

Hold our Metro representatives accountable based on the findings of an inquiry

Reform the system so the burden of regional infrastructure overruns is carried by all members of the region

North Shore Wastewater Treatment PlantTheir campaign sitesource · retrieved October 14, 2026

Making sure the North Shore isn't left carrying costs and consequences it didn't create.

We're being stuck with the heaviest burden of paying for the wastewater treatment plant's cost overruns, despite no direct accountability to North Shore voters at Metro Vancouver.

Hold our Metro representatives accountable based on the findings of an inquiry

Reform the system so the burden of regional infrastructure overruns is carried by all members of the region

Work collaboratively with other regional leaders and the province to create a new, accountable governance structure at Metro Vancouver and ensure that the North Shore is never again faced with the costs of poor decision making by leadership

North Shore Wastewater Treatment PlantTheir campaign sitesource · retrieved October 14, 2026

He is fully dedicated to stopping financial waste and protecting taxpayers.

FOCUSED VISION TO WIN BY A LANDSLIDE: Stop Tax Waste: Execute an immediate forensic audit of the staggering $3.86B North Shore Wastewater Plant budget disaster.

North Shore Wastewater Treatment PlantFiled statementsource · retrieved October 8, 2026

FOCUSED VISION TO WIN BY A LANDSLIDE: Stop Tax Waste: Execute an immediate forensic audit of the staggering $3.86B North Shore Wastewater Plant budget disaster.

North Shore Wastewater Treatment PlantFiled statementsource · retrieved October 8, 2026

District of North Vancouver — Council

6 mentioned it · you elect 6
Jim HansonElectedIncumbent

Jim will speak out loudly for accountability from Metro Vancouver for the North Shore Waste Water Treatment plant debacle and advocate for governance reform at Metro.

North Shore Wastewater Treatment PlantFiled statementsource · retrieved October 8, 2026

I will continue to vote for budgets that keep tax increases to the rate of inflation and that allocate an additional levy (1.5%) for infrastructure renewal.

Local government taxation has increased faster than inflation over the last decades, and District residents are facing an additional financial strain from the increasing utility levels caused by cost overruns at the North Shore Wastewater Treatment Plant.

My vote will be to curtail government spending to permit us to maintain operational tax increases to combat inflation .

At the same time, I will advocate for a disciplined financial plan that addresses our need for infrastructure renewal.

To balance our budgets, I will advocate for

North Shore Wastewater Treatment PlantTheir campaign sitesource · retrieved September 30, 2026

District residents are paying hundreds of millions of dollars for the over-runs at Metro Vancouver's Wastewater Treatment Plant. We cannot allow failures on that scale to happen again. We must invest responsibly in infrastructure, transportation, public facilities and services to maintain and improve the quality of life we've all come to enjoy.

Major capital projects need careful oversight and clear accountability. Council must understand costs and risks, test assumptions, demand clear reporting and explain the consequences to residents.

Infrastructure, transportation, public facilities and services shape daily life in North Vancouver.

North Shore Wastewater Treatment PlantTheir campaign sitesource · retrieved September 30, 2026

Due to the boondoggle that is the new Wastewater treatment plant the average North Vancouver household is going to be paying almost $600 per year more on their municipal taxes until 2054 to cover the extra cost! This extra burden on North Vancouver tax payers is why it is more important then ever to elect budget conscious counsillors.

Through my experience over 2 decades as President of the Parkgate Society Board of Directors, Program Director at a multimillion dollar non profit organization, and my experience in the private business world, I have overseen numerous large budgets.

North Shore Wastewater Treatment PlantTheir campaign sitesource · retrieved October 2, 2026
Catherine PopeElectedIncumbent

Catherine led the call for a public inquiry into the massive cost overruns at the North Shore Wastewater Treatment Plant. Council unanimously endorsed her motion, making the District the first municipality in Metro Vancouver to back an inquiry. She continues to fight for lower utility costs for NS taxpayers and change at Metro Van.

North Shore Wastewater Treatment PlantFiled statementsource · retrieved October 8, 2026

In March 2024, I sounded the alarm about the massive cost overruns on the North Shore Wastewater Treatment Plant. I led the charge for a Public Inquiry, deferred utility bills for NS taxpayers, an independent auditor, and greater transparency and accountability at Metro Vancouver through countless media interviews.

'The $235 million settlement must be used to reduce the financial burden on North Shore taxpayers impacted by these massive cost overruns.' – Councillor Catherine Pope

North Shore Wastewater Treatment PlantTheir campaign sitesource · retrieved October 14, 2026

Catherine led the call for a public inquiry into the massive cost overruns at the North Shore Wastewater Treatment Plant. Council unanimously endorsed her motion, making the District the first municipality in Metro Vancouver to back an inquiry. She continues to fight for lower utility costs for NS taxpayers and change at Metro Van.

Since her election in 2022, Catherine has helped deliver more affordable housing, a new toddler playground, new pickleball courts and expanded recreation, safer streets, youth-centre funding and greater transparency in Council decision-making.

North Shore Wastewater Treatment PlantFiled statementsource · retrieved October 8, 2026

In March 2024, I sounded the alarm about the massive cost overruns on the North Shore Wastewater Treatment Plant. I led the charge for a Public Inquiry, deferred utility bills for NS taxpayers, an independent auditor, and greater transparency and accountability at Metro Vancouver through countless media interviews.

North Shore Wastewater Treatment PlantTheir campaign sitesource · retrieved October 14, 2026

Catherine led the call for a public inquiry into the massive cost overruns at the North Shore Wastewater Treatment Plant. Council unanimously endorsed her motion, making the District the first municipality in Metro Vancouver to back an inquiry.

North Shore Wastewater Treatment PlantFiled statementsource · retrieved October 8, 2026

Finding other avenues for funding instead of raising taxes. The amount of taxes has grown quite substantially over the years and the services offered to residents in return are not visible.

There is already a huge burden on North Vancouver Residents with the Wastewater Treatment Plant costs for the next 30 years with no actual explanation or advocacy plans shared out. The wastewater plant went from $300M to $700M to $1B and now $4B – which doesn’t include the removal of the old wastewater plant and remedial efforts there

Why did it take 7 years for the residents on the North Shore to know about the $4B cost. We have reps from each municipality there – why were no yearly updates provided?

North Shore Wastewater Treatment PlantTheir campaign sitesource · retrieved October 14, 2026

Dan also serves as the spokesperson for the North Shore Neighbourhoods Alliance, a coalition of seven community associations seeking an independent, public inquiry into the Wastewater Treatment Plant project. This experience has strengthened his commitment to transparency, sound financial oversight, and ensuring regional bodies remain accountable to the communities they serve.

North Shore Wastewater Treatment PlantFiled statementsource · retrieved October 8, 2026

Dan also serves as the spokesperson for the North Shore Neighbourhoods Alliance, a coalition of seven community associations seeking an independent, public inquiry into the Wastewater Treatment Plant project.

North Shore Wastewater Treatment PlantFiled statementsource · retrieved October 8, 2026

This picks up candidates who used these exact words. Someone might care about it deeply and never name it, so read this as “who put it in writing”, not “who cares”.